DP world was a huge complex project. One of the biggest challenges was the coordination and installation
of the 18m X 10m LED screen in an open Atrium given a very short-time frame. This was one of the main
center attractions of the pavillion.
Once the installation took place the next challenge was ensuring the content ran smoothly across the 8K
display.
Another challenge was the design of the glass screen on the table on the first floor as people entered. Elements such as heat had to be considered from the LED table, the LED backing wall, and the printed acrylic models. The challenge was to ensure the LED didn’t melt the models. So much had to be considered to ensure the models kept their shape.
Installing the large LED screen into the open atrium took precision, weeks of planning
and teamwork. It was very rewarding to see the final result.
Content for the large LED screen had to be tested to ensure it would display correctly. Days of off-site
testing were conducted in parallel to the site installation, at the CTME offices, to allow the content
creators and CT's technology specialist time to test the integration and content performance.
For the glass screen weeks of planning and coordination with the fit-out contractor and model makers
ensured we met safety standards and kept the display intact.